wp-singular,post-template-default,single,single-post,postid-29925,single-format-standard,wp-theme-bridge,wp-child-theme-bridge-child,bridge-core-3.3.4.3,qode-page-transition-enabled,ajax_fade,page_not_loaded,qode-page-loading-effect-enabled,,vertical_menu_enabled,qode-title-hidden,qode-smooth-scroll-enabled,qode-child-theme-ver-1.0.0,qode-theme-ver-30.8.8.3,qode-theme-bridge,qode_header_in_grid,wpb-js-composer js-comp-ver-9.0.1,vc_responsive

Lancaster AI Hub Construction Update Q1 2026

Q1 2026 Construction Update:

  • Q1 ’26 construction at the LPE-01 Lancaster Campus conversion project focused on structural reinforcement, interior slab work and MEP install.
  • Roof reinforcement and structural deck replacement advanced.
  • Interstitial steel installation within the building continued to progress.
  • Building envelope work continued with insulated metal panel installation and deck removal across multiple halls. Façade demolition and insulated metal panel installation progressed along the north elevation.
  • MEP work also advanced with near-completion of underground plumbing. Sprinkler system installation continued above data hall areas.
  • First slab-on-grade concrete placement was successfully completed with additional slab pours scheduled through March.
  • Generator pad construction and curing operations were actively progressing.
  • Structural and interior build-out activities will continue through March and April.
  • The project is maintaining schedule progress while actively managing risks and safety.