12 May Lancaster AI Hub Construction Update Q1 2026
Q1 2026 Construction Update:
- Q1 ’26 construction at the LPE-01 Lancaster Campus conversion project focused on structural reinforcement, interior slab work and MEP install.
- Roof reinforcement and structural deck replacement advanced.
- Interstitial steel installation within the building continued to progress.
- Building envelope work continued with insulated metal panel installation and deck removal across multiple halls. Façade demolition and insulated metal panel installation progressed along the north elevation.
- MEP work also advanced with near-completion of underground plumbing. Sprinkler system installation continued above data hall areas.
- First slab-on-grade concrete placement was successfully completed with additional slab pours scheduled through March.
- Generator pad construction and curing operations were actively progressing.
- Structural and interior build-out activities will continue through March and April.
- The project is maintaining schedule progress while actively managing risks and safety.